PROJECT DE SMET S.A. TECHNOLOGIES & SERVICES EQUIPMENT FOR OPTTRADE LTD, KROPOTKIN

Project provided transportation of 303 units of equipment with the total weight of 287 mt.
As a result of delivery route development of oversized unit there was detected that radius of curvature of one of the tunnels on railway route didnt allow safe cargo transportation. To solve this problem there was obtained the permission to move tunnel railway. The permission to effect this procedure was obtained in the shortest term from Special Delivery Division of JSC Russian Railways Delivery Management Department.
The particular attention was paid to the unit with the following characteristics: length 25494 mm, width 4030 mm, height 3980 mm, weight 57 mt.
Transportation of this cargo has been made by 4-axle 64 mt capacity platform type transporter.
Disassembling of cargo detail parts which increased cargo size overage under the cargo owner agreement.
Installation of test frame to inspect whether rail transport with cargo can ride through all tunnels along the route without difficulties.
As a result of delivery route development of oversized unit there was detected that radius of curvature of one of the tunnels on railway route didnt allow safe cargo transportation.
With the help of railmotor car (model MPT-4) there was effected unprecedented procedure tunnel railway was moved. It took daylight hours only.





View all projects

Welcome to Maritime Days in Odessa!









Novorossiysk Port Terminal Ltd.

ph./fax: +7 (8617) 672373      ph.: +7 (8617) 763602
ph./fax: +7 (8617) 672383 fax: +7 (8617) 763603
e-mail: project@novpt.ru


Created by web-studio IDALGO

.