Project of delivery columns and hydrotreater unit to Tuapse refinery

NTP Ltd. delivered the heavy-lift equipment to Tuapse refinery by order of "Volga-Don-Transservice" Ltd.
June 21-23, 2014 3 columns and hydrotreater unit were delivered at the territory of Tuapse refinery. The total weight of equipment amounted to 461.5 tons, including units of 113, 97, 110 and 141.5 tons. Length of transported columns amounted from 34.8 to 44 meters.
June 3rd oversized vehicles were transported on a barge No. 8916 from the berth of "Volgogradneftemash" JSC. June 17th vehicles were delivered to a temporary berthing facility in Tuapse creek.
Barge No. 8916 equipped with easily removable rugged ramps length of 12 m that allows rolling out the cargo even under the difference between the barge and dockside deck levels. Containment system of barge pumps reduced the work labour input for ballasting / deballasting to a minimum level.
Rolling out of the cargo positions was carried out without setting down the barge, over a distance of 4 meters from the dockside! Standard windlasses of barge were used additionally for moorage and secure mounting of the barge while rolling out the positions.
Rolling out of all four units from the barge was completed in record time - just 36 hours!





View all projects

Welcome to Maritime Days in Odessa!









Novorossiysk Port Terminal Ltd.

ph./fax: +7 (8617) 672373      ph.: +7 (8617) 763602
ph./fax: +7 (8617) 672383 fax: +7 (8617) 763603
e-mail: project@novpt.ru


Created by web-studio IDALGO

.